fbpx

Bask Bokarina Construction Outlook

Updates for the Bokarina Beach Community 

GVG is committed to keeping Bokarina residents well-informed of progress relating to our Bask project. We’ll be posting Bask Bokarina construction updates at the beginning of each month to notify you of any significant milestones, changes, or disruptions related to site activities.

Due to the nature and scale of this project, please be aware that disturbances such as noise, dust, and temporary road closures will occur periodically.

We’re excited to be making progress at Bask, which upon completion will not only enhance the convenience and lifestyle of residents, but also that of the wider Bokarina Beach community. We look forward to welcoming vibrant new establishments, including restaurants and bars, to the nine retail spaces that will line Bokarina Boulevard.

We apologise for the inconvenience this may cause and appreciate your patience and understanding as we work towards enhancing our community.

Regards,


Keep an eye on this page for updates and important notifications.

To get in touch, please fill out the below form.

FIND OUT MORE

Site Updates

September 

  • Bulk excavation continues from ground level down to basement two. As a result of these earthworks, trucks will be entering the site via Kombi Street and leaving via Bokarina Boulevard throughout the day.
  • Toward the end of September there will be increased deliveries due to reinforcing requirements.
  • In late September, Kombi Street will be closed periodically to allow construction staff to install a new gantry site compound. Local resident access will always be permitted.
October

  • Bulk excavation will be complete by early October.
  • Following this, tower one’s crane will be installed. For the installation to take place swiftly, a section of Bokarina Boulevard will be closed to both directions of traffic for two days. 
  • The site team will continue to receive deliveries throughout the month.
  • Concrete pour to commence.

Frequently Asked Questions

Residents and their visitors will have local access to their property. We will ensure that one end of any street affected by a closure remains open.

Commencement Mid 2024 – Completion Late 2026

  • A traffic management plan will be established in coordination with local authorities for the many stages of works throughout the project. As the project sits on the corner at an integral roundabout, connecting the two residential streets either side, there will inevitably be some short term disruption throughout the project to vehicles and pedestrians and some night works to accommodate safe working conditions for all stakeholders. This will be carefully worked through.
  • Dust will be suppressed and managed throughout the projects particularly through the initial civil works with water.
  • The work hours will be in line with the local authorities directions and consideration of local neighbours.

Feel free to reach out for any further information via email to [email protected]

Support

If something is concerning you please reach out to discuss via the form below.

Please fill out your details and concern, and a member of the GVG team will be contact.